WYDOT Project Update
Buffalo Main St Improvement Project
April 3, 2025
For map of the project area discussed click here
Catch the latest update on the project with WYDOT Resident Engineer Stephan Charles.
Good news! Work is ahead of schedule. Construction season in full swing on Buffalo’s Main Street, and crews are making steady progress. Work is currently underway on the east side of Main St with concrete pours and sidewalk repairs. Expect to see contractors shift to the west side next week. .
Key dates to watch: pulverizing starts April 21st, and paving is set for May 5th, with the goal of wrapping up before Memorial Day.
WYDOT kindly asks drivers follow flagger directions and expect delays as this project moves forward.
For more information about the entire WYDOT Buffalo Main St Improvement Project click here