WYDOT Public Meeting
Buffalo Downtown Main St Project
Feb 27, 2025
The Buffalo Main Street project is entering its second year, with construction resuming on Monday 3rd March. At this Public Meeting held 27th February, WYDOT representatives outlined the scope of this season’s work and answered a variety of questions from business owners and members of the community,
The project aims to complete downtown work by Memorial Day weekend to minimize impact on tourist season. The scope includes utility work, sidewalk repairs, and ADA compliance updates.
The project also includes significant utility work by City of Buffalo, particularly water line replacement in Phase 5. The timeline extends through October 2025.
From Mon 3rd March, traffic control will be setup from Crazy Woman Square to Main Street Diner. East side of Main Street will be closed with traffic shifted to west side. Sidewalk access will be maintained except during specific repair work, and no parking will be allowed in active work zones.
For more information or to sign up for email updates contact:
Laura Dalles, WYDOT Public Relations Specialist
tel: 307 752 3022
e: [email protected]
For more information or questions about utility work contact:
Terry Asay, City of Buffalo
tel: 307 684 5566
Check 307NetInfo page dedicated to the project here
Open 0:30
Welcome & Introductions
Outline of 2025 project and Buffalo downtown work.
Questions
– Traffic flow 8:30
– Changes to traffic light at Fort St & Main St 10:45
– Uneven sidewalk repairs in front of Main St businesses 11:40
– Communication expectations for business owners regarding utilities 13:05
– Parking on Main St 20:00
– Alternative parking availability 21:00
– Snow removal during construction 22:10
– Work progression sequence 23:20
– Road lining and markings 26:25
– Handling business parking lots during construction 27:25
– Phase 5 construction approach 28:25
– Contacting businesses 29:15
– Reporting curb or sidewalk issues 32:00
– Sewer line replacement in Phase 5 34:15
Closing Remarks 34:35
Next Meeting Monday March 17th (details to be confirmed)
For Project Map click here
For Project Scop & Phases click here